Soterrament - Participatory process of urban transformation in Sant Feliu de Llobregat
#byebyevia Citizen participation process for urbanization on the surface generated by the burial of the railway.
Process phases
-
125/09/2018 - 08/11/2018
information
- Presentation of the process to the citizenship on September 25, 2018.
- Information on the activities, with its calendar of activities (participatory itineraries, mobile points, street activities, thematic workshops, etc.).
- Participation surveys: Identity of the new Sant Feliu, definition of equipment, housing and commercial activities and public space, uses and mobility
- Documentation
-
208/11/2018 - 08/01/2019
Presentation of proposals
Contribution of proposals by citizens taking into account the analysis framework (values, permanent uses, temporary uses, mobility, equipment, etc).
How many proposals can be made?
3 for each individual person (it can also be done by people not registered in the city)
How do we present the proposals?
We write the title and a description of up to 500 characters and assigning it one of these three areas / categories:
- Identity of the new Sant Feliu
- Public Space: uses and mobility
- Buildings: equipment, housing and economic activities
In what period can proposals be submitted?
Between November 8, 2018 and January 8, 2019
What do the Official proposals mean?
They are proposals that have been worked in person in the workshops of citizen dialogue and that the City Council moves to the platform.
Who technically validates the proposals?
The Technical Burial Office
With what criteria do the technicians value?
- They are not located in the municipality of Sant Feliu de Llobregat.
- They are not discussed in the participation process that defines the surface to be urbanized.
- They suppose insurmountable interferences with the constructive project of Burial.
- They suppose insurmountable interferences with the project of extension of the tram.
- They suppose the breach of urban regulations and / or they do not have economic viability.
- The proposal is included in other planned investments.
- The purpose of the action is not municipal responsibility or is outside the scope of study.
- They involve affectations in other disciplines in a derivative way, and they are not feasible.
-
308/01/2019 - 08/02/2019
Validation
This phase is internal work. There will be validation workshops and all the information and documentation will be provided.
-
426/02/2019 - ?
Account performance
- Presentation of the results report
- Information on how the process continues.
- Information of the citizen consultation
- Establish the citizen requirements to incorporate the specifications of the international ideas competition for the urbanization of the surface and the transformation of the city.
- Transmit to the architecture and urban planning offices what Sant Feliu we want, what needs and general requirements we have for this space and the interrelation with the rest of the territory.
- International project competition
- Green light to the burial consultation
- Consultation tracking web address: www.consultasoterrament.cat
- How to be part of the consultation
- How to find out about the consultation
- How to vote in the consultation
- Three projects to choose from: El passeig del Samontà, Gran Verger, Rambla Major.
- Question about the station: What do you consider to be the best proposal to preserve the memory of the station? Make a replica of the original station building in a different location from the current one or integrate a memory space of the original building, in the new Sant Feliu station.
- Frequent questions
- The Rambla Major proposal and the integration of a memory space in the new station are the winning projects in the Underground Consultation